A CCB is a formal organization that reviews, approves, or rejects project changes. It provides organized control over scope, cost, and schedule variances.
- 
Step 1: Define Governance 
- 
Identify members: project manager, sponsor, technical lead, QA, and functional heads 
- 
Set the frequency of meetings and quorum requirements 
 
- 
Step 2: Create a Change Request Process 
- 
Standardize a Change Request (CR) form that covers the description, impact, urgency, and reason 
- 
Use a ticketing tool or PPM system for traceability 
 
- 
Step 3: Define evaluation criteria 
- 
Assess the impact on the triple constraints (scope, time, and cost) 
- 
Evaluate the risk, benefit, compliance, and resource effect 
 
- 
Step 4: Document and track decisions 
- 
Maintain a Change Log to record approvals, deferrals, or rejections 
- 
Communicate choices with stakeholders and update project baselines 
 
- 
Step 5: Link CCB to Configuration Management 
The CCB ensures that only evaluated and approved changes affect the project baseline.